Energy and Infrastructure

Key developments

BIOMETHANE

The Minister for Climate, Energy and the Environment opened an Expression of Interest process for the Government’s €200 million biomethane capital grant scheme. We look at the announcement in our insights blog post: Energy update: Biomethane capital grant scheme.

Further announcements in this year’s budget included additional funding for district heating. We look at Budget 2027 in our briefing: Budget 2027: What it means for real estate and infrastructure.

FUTURE MARKETS

The October future markets industry workshop included the following indicative updates:

  • Non-priority dispatch renewables: Aspects of the current solution may need to be revisited, with further delivery work required once regulatory direction is confirmed.
  • Long duration energy storage: The decision on the procurement mechanism is expected imminently. It was indicated that the aim is to consult on contractual arrangements by the end of 2026.
  • Future arrangements for system services: There is a revised indicative go-live date of Q4 2028. A consultation on the approach to bridging the timing gap is anticipated. The updated Phased Implementation Roadmap (PIR4.0) is in development.
  • Capacity Remuneration Mechanism (CRM): A decision on the CRM 2.0 high-level design options is expected by the end of 2026.
  • MEC sharing: Implementation is in month two of the roadmap. EirGrid has also published an FAQ document on hybrid-co-located sites with MEC sharing (PDF 1.1 MB).

TRANSMISSION DEVELOPMENT PLAN

The CRU is consulting until 20 November on EirGrid’s Draft Transmission Development Plan 2026-2035. The Plan identifies 275 active projects, up from 223 in the previous plan. The core project list captures capital-approved projects at Steps four - six as at 31 March 2026. Delivery forecasts should be checked against the quarterly Transmission Infrastructure Delivery updates, which integrate outage, consenting and resource requirements into a programme. Inclusion is not assurance that reinforcement will arrive in time for a project’s commercial milestones.

For storage and flexibility investors, the draft draws a distinction between providing system services and substituting for network reinforcement. It indicates that existing system service arrangements do not explicitly target individual transmission constraints, and an effective storage alternative would require appropriately located assets capable of sustained delivery over longer durations. EirGrid is considering giving projects in its long-duration energy storage tender extra marks if they locate in constrained areas. The CRU asks whether the draft sufficiently demonstrates consideration of demand response, storage and other alternatives to system expansion. This potentially is an opportunity to seek greater transparency on the constraints flexible assets could address, how alternatives are evaluated and the procurement arrangements that would make them investable.

EU FRAMEWORK FOR CLIMATE RESILIENCE

A Framework Communication from the European Commission on an EU Framework for Climate Resilience (PDF 462 KB), as well as a proposed European Climate Resilience Law, is intended to strengthen Europe's ability to anticipate, prepare for, and manage climate risks. It proposes to embed climate resilience across policy areas. It identifies the role of businesses to scale up the resilience industry. Adapting Europe’s infrastructure and economy is expected to require investment of €70 billion per year, and the global market for climate adaptation solutions is projected to quadruple in size to €3.5 trillion by 2050.

The Framework could impact the development and financing of infrastructure, with the Commission proposing that a common forward-looking warming trajectory informs decisions on assets and investments, spatial planning and impact assessment, while embedding “climate-resilience-by-design” more systematically into EU funding and sectoral frameworks for energy, transport and critical infrastructure. Further information is available here: Commission presents Climate Resilience Framework for a better prepared and protected Europe.

HVO GENERATORS

The regulatory authorities are consulting until 11 November 2026 on the request to allow HVO generators to participate in intermediary arrangements.

CAPACITY MARKET CODE

Modifications to E7.5.1 on requirements for new capacity will be effective from 1 July 2027, post qualification for the T-1 2027/28 Capacity Auction. They explicitly add requirements to possess connection agreements / offers and planning permission for Applications for Qualification for a Capacity Year in respect of New Capacity for a Generator Unit or Interconnector comprising a Candidate Unit.

Further EU developments

ELECTRICITY

  • Critical infrastructure: ENTSO-E has made recommendations aimed at reinforcing Europe’s energy security framework, including developing harmonised risk assessments across the energy sector.
  • Electrification and prices: ENTSO-E’s positions on the Electrification Action Plan and the proposed legislation to future-proof electricity bills are available, along with a report on transmission costs’ recovery across Europe. Our insights blog post on the legislative proposal is available here: Energy update: EU proposes reforms to electricity network tariffs, smart metering and grid access.
  • Flexibility: ACER is consulting until 17 December 2026 on the preliminary version of an open-source electricity market model developed to assess flexibility needs across the EU (EU-Flex).
  • REMIT: The Estonian Competition Authority fined Futugrid Technologies €16,000 for manipulating the balancing energy market by placing a non-genuine bid, sending misleading signals to the market.
  • Strategy: ENTSO-E’s new strategy identifies five priority areas: system security, grid development and connections, adequacy and flexibility, operation of the future power system, and market integration and transparency.
  • Transmission: An ENTSO-E report maps how transmission costs are recovered across Europe in the context of common principles applicable based on the EU framework.

GAS

  • CAM Network Code: The European Commission is consulting until 10 November 2026 on amendments to Regulation (EU) 2017/459 establishing a network code on capacity allocation mechanisms in the gas transmission system.
  • Derogation: Luxembourg notified the European Commission of its decision to derogate from Article 60 (Unbundling of transmission systems and transmission system operators) of the Gas Directive.
  • EU Hydrogen Strategy: The European Commission is calling for evidence and consulting until 23 November 2026 on an EU Hydrogen Strategy. It indicates that particular attention will be paid to hard-to-electrify sectors where hydrogen adds the most value.
  • Hydrogen: ENTSOG is consulting until 30 October 2026 on its draft Hydrogen Infrastructure Gaps Identification Report for the Ten-Year Network Development Plan 2026. It also calls on promoters to submit information for the hydrogen infrastructure map update (PDF 419 KB).
  • Tariff network code: ENTSOG’s 2026 monitoring report on implementation of the Code indicates an overall high level of compliance.
  • Winter outlook: ACER indicates that Europe has historically low gas storage levels (75% in October 2026) and that refilling has become more expensive.

GREENHOUSE GASES

  • ETS and ETS 2 market stability reserve: The EU co-legislators agreed amendments to the Decisions on ceasing invalidation of allowances in the market stability reserve (as well as to the market stability reserve for buildings, road transport and additional sectors in ETS2). The Commission states that, under the current system, all emissions allowances in the reserve above 400 million are invalidated. Amendments will mean that the reserve can retain up to 700 million allowances as a buffer to support future market stability and predictability. Further information is available here: Political agreement on rules enhancing stability and long-term resilience of EU carbon market.
  • Benchmarks: The European Parliament adopted its position on the proposed amendments to the EU ETS Directive as regards revised benchmark values for the heat and fuel benchmarks for 2026 to 2030. The heat and fuel benchmarks are used under the EU ETS to determine free allocation of emission allowances for activities not covered by a specific product benchmark.
  • Methane regulation: The European Commission adopted a proposal to postpone by one year the application of monitoring, reporting and verification obligations for importers, as well as the provisions concerning methane intensity for importers and Union producers. Further information is available here: Commission proposes flexibility to methane importers to help save costs. The European Parliament has voted for longer periods of postponement, as outlined here: Methane rules: Parliament backs longer delay for energy importers and producers. The Parliament will now negotiate a final position with the Council.

RENEWABLE ENERGY DIRECTIVE

Commission Implementing Decision (EU) 2026/2316 on the recognition of the Roundtable on Sustainable Biomaterials EU RED voluntary scheme for demonstrating compliance with the requirements for biofuels, bioliquids, biomass fuels, renewable fuels of non-biological origin and recycled carbon fuels under the RED comes into effect on 5 November 2026.

Net Zero Industry Act

Member States will be required to report to the European Commission by 15 March 2027 on implementation of the NZIA in accordance with a template being consulted on until 11 November 2026.

CRITICAL RAW MATERIALS ACT

The European Parliament adopted its negotiating position on proposed amendments to the Critical Raw Materials Act. The Commission proposal would strengthen supply-chain risk assessment, board reporting and mitigation requirements for in-scope large manufacturers, including those producing renewable-energy equipment, energy-storage batteries, hydrogen equipment and heat pumps. The direction of travel is greater scrutiny of raw-material dependencies and sourcing resilience. The Parliament will now negotiate the final text with Member States.

STATISTICS

The European Commission’s report, EU energy in figures, is available.

Case law

ENERGY MARKET INTERVENTIONS

Regulation (EU) 2022/1854 on an emergency intervention to address high energy prices was time-limited and is no longer in force but case law arising from it is worth noting in any contractual negotiations in case analogous measures are introduced by the EU in the future, or by a Member State acting on its own initiative. (For background, we looked at the Regulation in our insights blog post here: Update on Energy Market Interventions in Electricity.)

Caps on wholesale market revenues

In C-633/23 (Electrabel and others), the applicants challenged the declaration model for Belgium’s levy on surplus revenues. National legislation set a cap of EUR 130/MWh (and EUR 180/MWh for electricity produced from solid or gaseous biomass fuels) for 1 August 2022 to 30 June 2023 and used presumptions to determine market revenues. The applicants argued this required them to declare revenues not received. The CJEU noted that the cap must apply to amounts reflecting actual revenues received by operators concerned. However, the relevant provisions of the Regulation read with the principle of proportionality did not prevent the amount of revenue to which a cap applies being determined based either on irrebuttable presumptions or on rebuttable presumptions provided that, in either case, they produced reasonable estimates representative of market reality during the relevant period. Account must be taken of the factual and technical factors characterising not only the situation of the operators and installations, but also the national electricity market. The CJEU also ruled that the Regulation did not prevent national legislation adopted after its entry into force from applying a similar cap to an earlier period. The EU had not regulated that earlier period or deprived Member States of their competence to do so (though States nevertheless had to exercise powers in compliance with EU law more generally).

In C-423/23, Secab, an operator of hydroelectric power plants, challenged Italian rules capping market revenues for 1 February 2022 to 30 June 2023 at reference prices ranging from EUR 56 to EUR 75/MWh, depending on the market zone. The CJEU held that the Regulation did not require such producers to retain 10% of revenues exceeding the cap. This was an option for Member States, not an obligation. Provisions in the Electricity Market Directive did not prevent a cap based on an arithmetic average of market-zone prices during 2010–2020, adjusted for inflation, provided it did not adversely affect investment in the renewable energy sector and ensured that investment and operating costs were covered. Member States could set a cap on the market revenues obtained by hydroelectric power plants without imposing a cap on revenues from the sale of energy produced from hard coal or a differentiated cap for producers of electricity from solar, geothermal or wind sources.

In C‑187/25, EVN Bulgaria Renewables challenged an assessment applying a revenue cap of BGN 191 per MWh, rather than BGN 350 (approximately EUR 180 per MWh), for 1 December 2022 to 30 June 2023. The approach also involved applying different revenue caps for renewable electricity producers, depending on whether contracts for compensation by way of premiums were still in force on 8 October 2022, including where the premium payable was zero. The CJEU held that relevant provisions of the Regulation do not prevent a national cap below EUR 180 per MWh, subject to compliance with Article 8(2). The Court also noted that the cap applies in principle to revenues from electricity sales in the balancing energy market unless the Member State exercises the Article 7(4) exclusion. The question concerning differential treatment was inadmissible because the reference did not sufficiently explain the producers’ respective situations, the objectives of the distinction or the reasons for uncertainty about Article 8(2)(a).

In C‑327/25, VETS Svoge, which owns hydropower plants, was subject to two separate contributions: (1) a monthly contribution of 5% of its revenues, net of VAT, from electricity sales, and (2) earmarked contributions flowing from the cap on revenues under the Regulation. When calculating the 5% contribution, VETS Svoge deducted the earmarked contributions from its electricity sales revenues. The relevant authority considered that there was no legal basis for this. The CJEU held that Article 8 of the Regulation does not prevent the 5% contribution (levied on all electricity sales revenues) operating alongside the revenue cap. The 5% contribution fell outside the Regulation. Questions concerning other EU energy and climate provisions and the free movement of capital were inadmissible because the reference did not sufficiently explain their relationship with the national legislation or the dispute. The Court lacked jurisdiction to interpret Article 17 (Right to property) of the Charter of Fundamental Rights of the EU (the “Charter”) because the scheme fell outside the Regulation and the reference did not show a connection with another act of EU law.

C-391/23 (Brăila Winds) is a Romanian reference which did not concern the Regulation. The CJEU found that the Electricity Market Directive and the European Climate Law did not prevent a tax on renewable electricity producers’ revenues above a specified price, notwithstanding the exemption of fossil-fuel and biomass producers. The tax pursued, at least partly, a budgetary objective and did not appear equivalent to fixing selling prices. Its compatibility with climate-neutrality objectives had to be considered in the context of the Member State’s overall measures. Its temporary application did not appear capable of significantly affecting greenhouse gas emissions. State aid and fundamental-freedom questions that had been referred were inadmissible (for several reasons including insufficient information), and the Court lacked jurisdiction to interpret Article 17 of the Charter.

Further applications are pending:

  • Advocate General Rantos gave an Opinion in Cases C-251/24 and C-392/24, taken by Axpo Energy Romania SA and others. The traders’ contribution was calculated by reference to the difference between selling and purchase prices, allowing a 2% profit margin for domestic transactions but none for electricity exports. Electricity producers were subject to a contribution on revenues above RON 450/MWh (approximately EUR 90/MWh). The AG considered provisions of the Regulation, the Electricity Market Regulation and Directive, and TFEU articles on quantitative restrictions on export. The applicants challenged Romanian contributions to the Energy Transition Fund applying from September 2022. The AG considered that provisions do not prevent the above approach in the absence of evidence that wholesale electricity prices were affected, provided Article 8(2) was satisfied. The contributions concerned margins rather than directly determining selling prices. Revenue caps had to reflect actual market revenues, and the referring court had to examine whether the traders’ retained margin covered their costs, whether the contribution risked reducing trading volumes and the number of active operators, and whether exemptions for certain producers were objectively justified. Surplus revenues had to be used for targeted measures supporting final electricity customers. EU law prevented national legislation making export transactions subject to a formula more onerous than that applicable to internal transactions and imports, unless it was justified by one of the grounds set out in Article 36 TFEU or an overriding reason in the public interest, and was proportionate to the objective pursued.
  • Advocate General Rantos gave an Opinion in C-467/24. 2Valorise HAM NV and others challenged a Belgian levy of 100% on revenues exceeding a cap of €130/MWh, or €180/MWh for electricity produced from biomass fuels, for 1 August 2022 to 30 June 2023. The AG considered arguments in relation to Articles 16 (freedom to conduct a business), 17 (property), 20 (equality), and 21 (non-discrimination) of the Charter, as well as principles of legal certainty and protection of legitimate expectations. The AG considered that Article 6(1), insofar as it provided for the capture of 100% of surplus market revenues, did not infringe Article 17 of the Charter (though Member States had the option to limit capture to 90%). Member States could introduce a cap below EUR 180/MWh, provided Article 8(2) was satisfied. Member States did not have to establish circumstances specific to their electricity markets to justify a lower cap, but the referring court had to verify whether the cap enabled producers to cover and recover operating costs and met the expectations of a reasonable investor, avoiding unfavourable effects on investments. Electricity produced from biomethane was excluded from the cap, but electricity produced directly from biogas using a cogeneration plant was not. Article 8(1)(b) did not require a higher cap for biomass facilities, provided Article 8(2) was respected. It was valid to exempt facilities with an installed capacity of up to 1 MW. Different presumptions could be used to determine the revenues of nuclear and other electricity producers, provided the differentiation rested on objective factors and produced reasonable estimates representative of market reality. The Regulation did not prevent a national cap applying to an earlier period outside its temporal scope, but such a cap had to be compliant with any other relevant EU law. Belgium’s reasons, including budgetary and administrative difficulties, did not justify maintaining the effects of the national legislation if it were found incompatible with EU law. The AG also noted that several actions for annulment of provisions of the Regulation, brought by energy companies, were pending before the General Court at the date of his Opinion.

Temporary Solidarity Contribution (from surplus profits generated by businesses with activities in the crude petroleum, natural gas, coal and refinery sectors)

In the context of several applications which are pending, Advocate General Rantos provided Opinions that the Regulation, including Article 14, was validly adopted under Article 122(1) TFEU, notwithstanding the contribution’s fiscal nature, and without requiring unanimity in the Council. Article 14(1) required that surplus profits generated by companies and permanent establishments with activities in the crude petroleum, natural gas, coal and refinery sectors were subject to a mandatory temporary solidarity contribution, unless Member States had enacted equivalent national measures. A summary is available by clicking here (PDF 145 KB). Further details of the individual applications are below:

  • In C‑358/24, Varo Energy Belgium and others challenged Belgian legislation establishing a temporary solidarity contribution for 2022 and 2023, calculated at EUR 6.9 per tonne of crude petroleum processed by refining companies and EUR 7.8 per cubic metre of products released for consumption by oil companies designated as primary participants. The measure could qualify as an “equivalent national measure” for refining companies despite using a different calculation method, provided it shared similar objectives, was subject to similar rules and generated comparable or higher proceeds. The Regulation did not prevent its extension to oil companies designated as primary participants, but that extension fell outside the Regulation. Articles 30 and 110 TFEU did not prevent the contribution provided it applied irrespective of product origin and neither taxed products from other Member States more heavily than similar domestic products nor afforded indirect protection to other domestic products. The measure was not State aid provided it did not differentiate between operators in comparable factual and legal situations, a matter subject to the referring court’s factual assessments.
  • In C‑533/24, Vermilion Energy Ireland and related companies challenged the validity of Chapter III of the Regulation and the Irish legislation implementing it. The Irish contribution applied to 2022 and 2023 at 75% of taxable profits exceeding 120% of average taxable profits for 2018–2021, without allowing losses incurred before 2018 to be taken into account. The AG considered that Chapter III was validly adopted. He distinguished the Regulation, adopted before the end of 2022 and not retroactive, from the Irish Act, which entered into force on 2 August 2023 and had retroactive effect for 2022. The retroactivity was justified by the objective of general interest and respect for legitimate expectations: the Regulation expressly covered 2022 and Irish authorities had announced its application before that year ended. The 75% rate and treatment of previous losses fell within Member States’ discretion (but remained subject to the Charter). Neither infringed Articles 16 and 17 of the Charter, subject to the referring court’s factual findings. Relevant considerations included the contribution’s temporary application only to surplus profits, the applicants’ effective overall tax rate of 25.2% for 2022, and the continued deductibility of historical losses for standard corporation tax.
  • In C‑153/25, Acea Produzione and others challenged Italian legislation imposing a temporary solidarity contribution, not only on operators in the sectors covered by Article 14 of the Regulation, but also on electricity producers and other operators, including resellers, distributors and importers (some of whom were also subject to the Article 8 market revenue cap). The AG considered that the Italian measure should be classified as an “equivalent national measure” only in respect of the sectors to which Article 14 applies. Its application to additional operators did not deprive it of that status, provided Article 14 requirements remained fulfilled for operators within its scope. Nor did Article 14 prohibit Italy from imposing a contribution on other operators. The Regulation did not exhaustively harmonise taxation, and Member States retained their fiscal competence outside its scope, subject to EU law and without undermining the Regulation’s effectiveness. For producers already subject to the market revenue cap, the AG relied on Article 8(1)(a), which permits national measures further limiting market revenues, provided the conditions in Article 8(2) are satisfied. The measures overlapped only for December 2022. The referring court must verify whether combined application of the two measures enabled producers to cover and recover operating costs and achieve a profitability level in accordance with the expectations of a reasonable investor, avoiding unfavourable effects on investments.

CHARGES FOR ACCESS TO THE NETWORK

C-199/25 concerned an action brought by ten Flemish electricity and gas distribution system operators (“DSOs”) challenging a regulatory decision setting the charging method applicable to electricity and gas distribution for 2025–2028.

A first question concerned whether the decision, by allowing network tariffs to include costs linked to public service obligations (“PSOs”) not otherwise financed, was compatible with the prohibition in Article 18(1) of the Electricity Market Regulation on including “unrelated costs supporting other policy objectives” in network access charges.

“Network charges” under Article 18(1) are only one of three components of the final customer price, covering only costs directly linked to network use, connection or reinforcement. PSO costs fall outside that concept. Article 9 of the Directive does not prevent DSOs passing PSO-implementation costs to final customers, provided financing is non-discriminatory and transparent. How renewable energy support is funded (subsidies, tax, or consumer pass-through) is an energy-policy choice outside the regulator’s competence. Classifying PSO costs under “network charges” for accounting purposes does not by itself breach Article 18. The referring court must verify whether those costs are, in substance, clearly dissociated from the network-charge calculation method and remain transparent. The relevant articles do not prevent national legislation allowing unfinanced PSO costs in network tariffs, provided they are excluded from the regulator’s charge-setting method and clearly distinguished from those charges.

The second question was whether a tariff method based on DSOs’ embedded (historical) costs, without apparent efficiency control, met the requirement that charges reflect an efficient, comparable operator’s costs. Article 18 prescribes no particular methodology, only requirements any method must meet. Basing a methodology on historical data as a starting point does not of itself breach Article 18. The regulator’s method appeared to review the reasonableness of declared costs against an efficient comparable operator, including an inflation adjustment and an efficiency incentive. The relevant articles do not prevent a historical cost-based pricing method, provided it complies with Article 18 and includes mechanisms reasonably aligning resulting costs with those of an efficient, comparable DSO.

REMIT: auction rule compliance is noT Necessarily a safe harbour

Advocate General Rantos delivered his Opinion in Case C‑398/25 concerning alleged manipulation of Austria–Switzerland electricity transmission capacity auctions. The AG’s key conclusions are:

  • Cross-border scope: REMIT applies to transmission capacity trading between Austria and Switzerland in both directions, including by Swiss companies.
  • Auction compliance is insufficient: Returning annual capacity and bidding to repurchase it in the same monthly auction may constitute manipulation if it gives false or misleading signals or fixes, or attempts to fix an artificial price without legitimate reasons. The national court must assess all the circumstances and the strategy is not automatically unlawful.
  • “Use-it-or-sell-it”: The strategy does not, in itself, breach that principle.

Further domestic developments

LEGISLATION

The Development (Strategic Gas Reserve) Act 2026 has been commenced by the Development (Strategic Gas Reserve) Act 2026 (Commencement) Order (PDF 133 KB).

The Government approved revised Heads of the Electricity (Supply) (Amendment) Bill 2026. The Bill is intended to support the management of forestry and vegetation-related risks across electricity infrastructure, strengthen ESB Networks’ powers to address risks and enhance restoration powers following severe weather events and other emergencies.

Further CRU business

CUSTOMERS

The CRU’s decision on additional customer protection measures for household electricity and gas customers 2026/27 is available.

EU TRADING

In the 4th amendment of the Core Long-term Transmission Rights’ proposal, Core TSOs made changes to the regional design to include the border between the Single Electricity Market on the Island of Ireland and France, once the Celtic Interconnector is energised. The CRU has published its approval.

Further SEM Committee business

All Island Programmes

The approach to governance and revenue recovery arrangements for all island programmes outlines current programmes and governance structures.